On-Site Tank Fabrication Under Deadline
- Share on Facebook
- Share on LinkedIn
- Share on Email
-
-
Share Link
- Tank Components
- August 22, 2022
- 1 Minute Read
- Share on Facebook
- Share on LinkedIn
- Share on Email
-
-
Share Link
Tight Turnaround in Texas
We often have a small window to construct new tanks on-site due to working within the duration of a planned shutdown. This particular job took that concept to a whole other level. We only had one month to demolish two existing tanks with peripheral structures and fabricate a new tank in its place.
The Solvay project was one of the most challenging jobs Paul Mueller Company completed because of the tight time schedule. The scope of this Texas project included demolition and new construction of a tank and stair tower, ductwork, and structural work.
The tank weighed more than 1 million pounds and was 75 feet tall and 33 feet in diameter. It contained another shop-constructed tank, a complex shelf system, and shell-in-tube heat exchangers. Due to the project's complexity, the tank was built conventionally on a temporary foundation. The tolerance for this project was too small for the tank to be fabricated using a jack system.
The old ductwork and tank were demolished during a month-long shutdown period, during which the new tank and ductwork also needed to be installed. To ensure the plant could reopen on schedule, an hour-by-hour all-day and night work schedule was created as part of the project bid.
The welds for this job were thoroughly inspected with a dye pen and X-ray. Out of the 16,000 feet of welds inspected, only two inches needed to be repaired because of the thoroughness of the new welding procedure used by Paul Mueller Company, called "back purging."
We Can Work Within Your Planned Shutdown
No job is too big a challenge for Paul Mueller Company. Let us help you plan your next shutdown. We can work within your schedule to make your next field construction project successful.
More from Mueller Academy
- Introducing Our New Membrane-Based Water for Injection (WFI) Skids
- Manway Gasket Installation & Bushing Adjustment
- How to Decide Between a Horizontal & Vertical Milk Tank
- MES & PSG Feedwater Quality Requirements
- Finding the Right Finish: Understanding Polishing
- Increase the Capacity of Your Clean Utility Equipment
- Balancing a Mueller Multiple Effect Still (MES)
- The Different Types of Steam in Industrial Steam Generation
- How a Pure Steam Generator Works